Marangoni Design School

YEAR

2018

LOCATION

Design District Miami

THE CHALLENGE

Build-out for 20,000 sq. ft. learning facility. Coordination with client's representative in Italy, early procurement and processing through US Customs, and working together with private provider to secure permit and timely inspections to assure completion for student enrollment.

HIGHLIGHTS

Demanding exactitude of minimalistic lines throughout the project to achieve the design intent.

INITIAL / FINAL DATE

April 2017/January 2018

COST

$2.4M